That’s the percentage of days that the Hydro project will not be producing any electric.
This information comes straight from the VLF website.
The operating head for this turbine design is between 1.4 and 2.8 meters of head.
Did some quick number crunching from the COE Rock Island web site on river levels. Take the pool level at L&D 21 and subtract the tailwater at L&D 21 and you get the “head”.
In the last 12 years the level that falls below the minimum operating head pressure design of these turbines would amount to them not operating 39.79% of the time. The worst years would be 1998 of not operating for 177 days ( 48.5% )and the best would be 2006 when they would only be down 55 days ( 15%).
If you want to look at the sheet I have done, let me know and I will paste it up.